Bathroom Case Study
Below is a start to finish bathroom project we completed recently. Unlike most bathroom companies online, the pictures are ours and provide the highest of finishes on all our bathrooms we design and install.
These are the before photo shots of the bathroom.
Day 1 – Rip out floors and lay pipes.
Day 2 – Finish under floor plumbing lay new floor.
Day 3 – Construct wet floor area.
Day 4 – Plasterboard walls and cut out for shower.
Day 5 – Plaster ceiling and make good walls.
Day 6 – Fit fitted furniture.
Day 7 – Lay floor matting for under floor heating tile we floor latex floor.
Day 8 – Tile floor.
Day 9 – Fit bath and start tiling walls.
Day 10 – Box round bath plump taps and tile.
Day 11 – Finish tiling.
Day 12 – Grout Tiles.
Day 13 – Fit basins towel rails.
Day 14 – Fit doors plinths WC bath panel and clean.
Completed finished room.